12.17 (Item #17) Approve Lease/Leaseback #1663 Final Change Order #1663-001 (DEDUCTIVE)to Taber Construction, Inc. for Portable Replacement 2014 at Eagle Peak MS, Gregory Gardens ES, Silverwood ES and Woodside ES |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
On December 11, 2013 the Board of Education awarded Lease/Leaseback Agreement #1663 to Taber Construction, Inc. for a Guaranteed Maximum Project Cost of $7,998,033.62 for the provision of all tools, materials, labor and equipment necessary to complete Portable Replacement 2014 Project at Eagle Peak MS, Gregory Gardens ES, Silverwood ES and Woodside ES. As a result of unused contract contingency, a single, final deductive change order in the amount of <$491,105.44> is necessary. This single, final change order will result in a final revised contract value of $7,506,928.18 and represents a decrease of 6.14% to original contract value. |
|
|
Funding:
|
|
Recommendation
|
Approve Lease/Leaseback #1663 Final Change Order #1663-001 (DEDUCTIVE)to Taber Construction, Inc. for Portable Replacement 2014 at Eagle Peak Montessori School, Gregory Gardens Elementary School, Silverwood Elementary School and Woodside Elementary School. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Tim Cody - Program Manager |
|
Signed By: |
|
Dr. Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Moved, Member seconded to approve the Original motion 'Approve all Consent Agenda items.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Barbara Oaks | Yes | Brian Lawrence | Yes | Cheryl Hansen | Yes | Lynne Dennler | Yes | Linda Mayo | Yes | |
|
|
|
|
|
|